• ☆ Yσɠƚԋσʂ ☆@lemmy.mlOP
    link
    fedilink
    arrow-up
    10
    arrow-down
    1
    ·
    9 months ago

    Yeah the framing there is kinda silly, but it does seem like the whole fab reshoring thing has been plagued with problems. The more interesting parts of the article were that the time to build fabs is increasing, especially in recent times

    Things look even worse when you look at specific decades. In the 90s and 2000s, the U.S. was pretty fast and saw average construction times of about 675 days. In the 10s, that number dramatically increased to 918 days. Meanwhile, China and Taiwan were going at a much faster pace that decade, with an average completion time of 675 and 642 days, respectively.

    and the number of fabs overall is at all time low

    Naturally, the amount of fabs the U.S. is making at all has also declined. In the 90s, 55 fabs were constructed in the U.S., dropping to 43 in the 2000s and then to 22 in the 10s. At the same time, China is massively accelerating its fab construction, from 14 in the 90s to 75 in the 2000s to 95 in the 10s.

    It’s also not just a month difference for the delays

    The findings aren’t surprising, as many high-profile fabs have missed their original targets for production. TSMC’s Fab 21 in Arizona recently added a one-year delay, Intel’s Ohio fabs are apparently slipping from 2025 to late 2026, and Samsung delayed a Texas-based foundry to 2025 due to not receiving its CHIPS Act funds.

    And there are a couple of related data points from TSMC and Samsung regarding fab construction

    https://www.tomshardware.com/tech-industry/us-government-doles-out-paltry-dollar35-million-of-the-dollar52-billion-chips-act-warns-of-possible-delays-in-intel-and-tsmc-fab-buildouts

    https://www.tomshardware.com/tech-industry/semiconductors/us-govts-sluggish-chips-act-payouts-slam-the-breaks-on-samsungs-fab-company-delays-mass-production-at-texas-fab-to-await-further-chips-funding-report

    So, while I agree that EPA regulation isn’t the core problem here, I think it’s pretty clear that US is having trouble with the whole reshoring idea.

    • Water Bowl Slime@lemmygrad.ml
      link
      fedilink
      arrow-up
      19
      ·
      9 months ago

      TSMC got delayed because the local union demanded they stop replacing them with foreign workers and Samsung is delaying their construction because they’re fighting with Intel for subsidies.

      Lol and we call these companies “job creators” when we have to fight them to even hire us. And why can’t Samsung pull themselves up by their bootstraps and free market themselves a factory, hmmm? 🤔

      • HexBroke [any, comrade/them]@hexbear.net
        link
        fedilink
        English
        arrow-up
        18
        ·
        9 months ago

        And why can’t Samsung pull themselves up by their bootstraps and free market themselves a factory, hmmm

        Or not be the largest chaebol conglomerate as a result of a US occupation then US backed military dictatorship in South Korea for decades

        • PolandIsAStateOfMind@lemmygrad.ml
          link
          fedilink
          arrow-up
          16
          ·
          edit-2
          9 months ago

          In Poland we call it “Szajsung” from German “scheisse”, because in 90’s we were flooded with their products which were drastically less reliable than what we were used to from Polish, Soviet and East German house aplliances and electronics.

    • WashedAnus [he/him]@hexbear.net
      link
      fedilink
      English
      arrow-up
      8
      ·
      9 months ago

      In the 10s, that number dramatically increased to 918 days.

      This is what I was told by a coworker who had been in the semiconductor industry for decades (can’t ask him for sources now because he’s dead):
      During the Obama administration, they set up a tax cut to incentivize companies to build more factories, where you would get a tax break if you filed plans within a certain time frame, but you only needed to build one building to take advantage of it on the planned future construction. As an example, Intel slowly built a new fab in Arizona, and, once it was completed, they left it empty for years, only starting to install equipment in 2019. This facility was also built with the move to 450mm wafers in mind, so it was much larger than previous fabs. The move to 450mm wafers never happened, and probably never will.

      A big part of the speed is the extremely poor mid to long term planning. Constant rework because of constantly changing demands, slashing workforces during slow periods and then struggling to fill positions long after they should have been filled, and more bullshit as you can imagine.